  | 
 
Multi-Leveled - Rail Road Tie Walls
 
1989: Multi-Leveled - Rail Road Tie Walls 
 
Huntington, New York  
 
ITEM- RRT - 04 
 
- Stage 1 - Property Plan and site survey.
 
- Stage 2 - Site preparation to include removal of old; decks, bush and trees  with our Bobcat.  Complete Demolition of all old wall structures. Latter all  debris was hauled to land fill and discarded.
 
- Stage 3 - Bobcat used to backfill behind all walls after construction was completed. Mult-Teared construction due to extreme incline of terrain.
 
-  All timbers used were; 30 year cca, grade 1, pressure treated lumber.
 
 
 | 
 |